In accordance with the provisions of the German regulation on reserve power plants (abbr. Reservekraftwerksverordnung - ResKV, s.4) Transmission System Operators are obliged to publish a call for interest when the regulatory authority (Bundesnetzagentur) has identified an additional requirement of generation capacity for the network reserve (ResKV, s.3).

The purpose of the network reserve is to maintain generating capacities to guarantee the safety and reliability of the electricity supply system. According to the German regulation on reserve power plants (“Netzreserveverordnung”), German transmission system operators jointly proceed an annual system analysis that includes a consideration of the guaranteed generating capacities available for demand-relevant periods within the following years. The system analysis indicates the total reserve demand for a safe and reliable operation of the electricity supply system. The comparison of the entire reserve demand with the reserve capacities that are already available results in an additional demand for network reserves for the respective time period in question.

Call for expressions of interest in accordance with § 4 para 2 of the German Regulation on Network Reserve (NetzResV) for the winter period 2024/2025 (1st October 2024 - 31st March 2025)

In accordance with the provisions of the German regulation on network reserve of power plants (Netzreserveverordnung) as last amended on December 22nd  2023, the German national regulatory authority (Bundesnetzagentur, NRA) has examined the requirement for additional reserve power for the network reserve as determined by the German transmission system operators for the winter period 2024/2025, and has published the associated report in accordance with § 3 para 1 NetzResV.

In the report of the German NRA dated April 30th, 2024, an additional demand for generation capacity for the network reserve in the total amount of 1367 MW is determined for the winter term 2024/2025, for the coverage of which an expression of interest pursuant to §4 NetzResV is initially launched. The total amount of network reserve capacity to be acquired may change depending on the sensitivity to network congestions and has to been evaluated in the context of possible alternatives within the congestion management as well as the current political situation.

The German transmission system operators hereby invite interested power plant operators to submit expressions of interest in accordance with § 4 (2) NetzResV for the participation of their power plants in the network reserve in the period from 2nd May 2024 to 21st May 2024 8 a.m. CET. To submit an expression of interest, interested operators are required to complete the documents supplied for this purpose and return send them to the responsible transmission system operator, both electronically or in printed form.

  • for Germany: the relevant connecting transmission system operator
  • for Italy and Switzerland: TransnetBW GmbH
  • for France and Luxemburg: Amprion GmbH

Details of the specific prerequisites and requirements for the plants and/or plant operators, including the geographical network region in question and the technical parameters involved, are included in the documents provided.

The deadline for submitting expressions of interest for participation in the network reserve is at 8 am on May 21st, 2024, 8 a.m. CET. The electronic submission of the signed documents is relevant for the on-time submission.

Possible resulting contracts will depend on approval by the German NRA, especially regarding the selection of plant operators to be contracted and resulting financial obligations upon the responsible transmission system operator. There is no legal entitlement to conclude a contract.

TenneT TSO GmbH reserves the right to change the published information without further announcements.

Contact for expressions of interest to be submitted to TenneT TSO GmbH:

Contacts

TenneT logo

TenneT Network Reserve

TenneT TSO GmbH
Bernecker Straße 70
95448 Bayreuth

Expired calls for interest

Test      
Delivery period Tender deadline Inclusion date of plants into network reserve Requirement in MW
Winter 2023/2024 May 15th, 2023 October 1st, 2023 1334
Winter 2022/2023 May 15th, 2022 October 1st, 2022 1424
Winter 2017/2018 May 15th, 2017 October 1st, 2017 1600
Winter 2019/2020 May 15th, 2015 October 1st, 2019 1600
Winter 2016/2017 May 15th, 2015 October 1st, 2016 3198-4212
Winter 2015/2016 May 15th, 2015 October 1st, 2015 489-1388
1st quarter 2015 October 15th, 2014 January 1st, 2015 545
Winter 2017/2018 May 15th, 2014 October 1st, 2017 3076
Winter 2015/2016 May 15th, 2014 October 1st, 2015 1414
Winter 2015/2016 May 15th, 2014 October 1st, 2015 1439
Winter 2014/2015 May 15th, 2014 October 1st, 2014 64