DolWin3
The DolWin3 project is the third offshore grid connection in the so-called DolWin cluster. The offshore grid connection connects two wind farms in the south-western part of the German North Sea with the onshore transmission grid. Around 160 kilometers of cable were laid for this purpose: 80 kilometers each at sea and on land.
The DolWin3 project is the third offshore grid connection in the so-called DolWin cluster. The offshore grid connection connects two wind farms in the south-western part of the German North Sea with the onshore transmission grid. Around 160 kilometers of cable were laid for this purpose: 80 kilometers each at sea and on land.
- DolWin3
About the project

In July 2017, the heart of the DolWin3 grid connection, the DolWin gamma converter platform, was installed at sea. The platform, built in Warnemünde, Mecklenburg-Western Pomerania, covered a six-day journey along the German and Danish coasts to its final location in the North Sea. There it was successfully installed over several days on the substructure already installed in 2016 - the so-called Jacket. The 900 megawatt grid connection is in operation since September 2018. With DolWin3, more than one million households can be supplied with clean wind energy.
Connecting concept
The electricity generated at sea is collected in the wind farm's own transformer station. From there the energy is transported to TenneT’s offshore converter platform via a 155 kilovolts three-phase alternating current (AC) cables. The conversion of AC to direct current (DC) takes place in the offshore converter station. The electricity is then transported by submarine and underground cable to the corresponding land station. Here, the electricity is converted back into AC and fed into the TenneT extra-high voltage grid.
