Procedure and lead time

In the case of a new connection, TenneT will discuss the possibilities with you, and together we will explore, if necessary with the regional grid operator, what the best connection option is for your particular situation.

Three phases in the procedure

Information phase, basic design phase, construction phase

This phase is used to hold talks with the customer. Based on the outcome, TenneT will make a quick scan so as to identify the substation to which the customer can be connected, provide a rough timeline for doing this and estimate the total costs. On request TenneT will also submit an offer for a basic design. In order to arrive at a good quotation for the basic design, the customer must fill in the 'information request form for the customer connection (basic design)'. 

The basic design will work out the request for a connection in greater detail, including a project description, planning aspects, licences and the technical properties of the connection. Subject to approval, this phase will end with signature of the construction agreement, in which the planning and the costs will be agreed.

This phase formally starts at the time of signature of the construction agreement. Throughout the entire construction phase, TenneT will hold regular talks with the customer for example to close an Connection and Transport agreement.

Construction procedure: 'Hessels'

A customer who wants a connection to the grid with a connected load greater than 10 MVA can have TenneT perform the work or subject the connection work to public tender

If the customer has the connection work performed by someone other than TenneT, no connection fee will be charged for the connection in question other than for the tasks performed by TenneT in association with the connection work, such as ensuring that the safety and reliability of the grid is maintained. TenneT and the customer shall agree on a reasonable fee for these tasks, which will be specified according to task and based on the number of hours actually spent by TenneT on them. Labour costs for the hours spent on each task shall also be specified. In addition to establishing the connection, the connected party may also request tenders for work involved in maintaining the connection, modifying the connection and removing the connection (removal).

European codes

The new European connection codes came into effect in the course of 2019

The new European connection codes came into effect in the course of 2019. Based on English titles, these codes are designated using the following abbreviations:

  • NC RfG: This code contains requirements for the grid connection of generators/electricity-generating units and comes into effect on 27 April 2019.
  • NC DCC: This code contains requirements for the grid connection of demand facilities and closed distribution systems and comes into effect on 18 August 2019.
  • NC HVDC: This code contains requirements for HVDC connections and electricity-generating units with direct current connections and comes into effect on 8 September 2019.

The European codes can be found at various locations, including TenneT locations.

Compliance verificatieverplichtingen

The European codes set all kinds of requirements for demonstrating that the connected facilities actually comply with the European codes, these exceeding those incorporated in current Dutch codes.

The European codes set all kinds of requirements for demonstrating that the connected facilities actually comply with the European codes, these exceeding those incorporated in current Dutch codes. These measures constitute what we call compliance verification.

For small electricity-generating units (up to 1 MW), it is sufficient to submit a certificate. For larger electricity-generation units and for demand facilities whose supply is driven by demand, more extensive testing is required to verify compliance.
Together with regional grid operators, TenneT has drawn up a document that provides detailed explanations of the tests required for the specific facilities.

This document, which is currently limited to electricity-generating units, can be consulted on the website of branch association Netbeheer Nederland (only Dutch).