Our key tasks

We are primarily tasked with providing power transmission services, system services and facilitating the energy market. Our core tasks follow from our appointment as grid operator under the Dutch 'Elektriciteitswet' (E-wet) and the German 'Energiewirtschaftsgesetz' (EnWG).


Explore our key tasks


TenneT presents Hub and Spoke concept for large scale wind energy on the North Sea.

Read more
Our grid

TenneT manages the high-voltage grid in the Netherlands and large parts of Germany. TenneT transmits electricity at 110,000 volts (110 kV) and higher. With over 22,500 kilometres of high-voltage lines, we cross borders and connect countries.

Explore our grid

Grid maps

Maps of our onshore and offshore high-voltage grid.

To grid maps
Electricity market

The energy sector is developing rapidly. The process of European market integration began some years ago. Its purpose is to create a single European market that enables market parties to trade gas and electricity across national borders easily and efficiently.

Explore the electricity market

Transparency data

We provide transparency data on our operations on our Dutch and German transparency page and on ENTSO-E. 

To transparency pages

TenneT is a leading European electricity transmission system operator (TSO), with activities in the Netherlands and in Germany. We strive to ensure a reliable and uninterrupted supply of electricity in our high-voltage grid for some 41 million people.

Explore our company

We are TenneT

Meet us
News German Project

TenneT switches DolWin2 offshore grid connection significantly earlier

Downloads & Contact
  • Significant optimisation of the repair processes and work acceleration have further reduced the anticipated switch-off
  • Re-connection has already taken place on 8 January 2017

The transmission system operator TenneT has already reconnected the DolWin2 offshore grid connection, which has been disconnected since 07 November 2016, on 07 January 2017. Since then, the offshore wind farms it connected were able to transfer power back to shore. This meant that reconnection took place more than 11 weeks earlier than the expected date of 27 March 2017. This significant reduction in switch-off time was made possible thanks to tremendous efforts on the part of all participating companies as well as the involvement of the involved landowners and authorities. The dry weather during the months of November and December, which was very unusual for the time of year, was also a decisive factor in the rapid progression of work. 

Essential for this acceleration was the close and constructive cooperation between TenneT and ABB, the general contractor commissioned for this project. These include, among others, the establishment of additional resources and the optimisation of the efficiency of repair work in the field of cable routes. This interaction enabled a decisive time optimisation of the repair process. The result was that DolWin2, and therefore also the connected offshore wind farms, were reconnected to the grid considerably earlier than initially assumed. 


During the test phase, a DolWin2 cable component failed repeatedly. In June 2016, TenneT took the decision to temporarily take the system offline and requested ABB to remedy the defects. This work was immediately started at full speed. The preparations for the acceptance process can now be continued after the successful conclusion of this rectification work. By means of this, TenneT was able to fulfil responsibility as a transmission system operator to ensure there are no problems later on during grid operations and that subsequent charges for electricity consumers are avoided to the greatest possible extent. In this regard, TenneT will also consistently carry on working to keep the possible burden on electricity customers as small as possible. TenneT fully relies on ABB, the general contractor for this project, to ensure that the DolWin2 offshore grid connection is brought up to acceptance condition.   

Facts and figures regarding DolWin2

  • 135 kilometre-long cable in high voltage direct current transmission technology (HVDC) with a maximum transmission capacity of 916 megawatts
  • 90 kilometres of land cable, 45 kilometres of subsea cable
  • Grid connection point: Dörpen-West 

Do you want to know more?

Mathias Fischer

Pressesprecher - Region Nord, Netzausbau offshore sowie onshore Nord, NordLink, Unternehmen

0049 (0)921 50740-4044

Do you want to stay informed?

Like the

facebook page

Go to Facebook page