Reserve power plants
In accordance with the provisions of the German regulation on reserve power plants (abbr. Reservekraftwerksverordnung - ResKV, s.4) Transmission System Operators are obliged to publish a call for interest when the regulatory authority (Bundesnetzagentur) has identified an additional requirement of generation capacity for the network reserve (ResKV, s.3).
The purpose of the network reserve is to maintain generating capacities to guarantee the safety and reliability of the electricity supply system. According to the German regulation on reserve power plants (“Netzreserveverordnung”), German transmission system operators jointly proceed an annual system analysis that includes a consideration of the guaranteed generating capacities available for demand-relevant periods within the following years. The system analysis indicates the total reserve demand for a safe and reliable operation of the electricity supply system. The comparison of the entire reserve demand with the reserve capacities that are already available results in an additional demand for network reserves for the respective time period in question.
Call for expressions of interest in accordance with § 4 para 2 of the German Regulation on Network Reserve (NetzResV) for the winter period 2023/2024 (1st October 2023 - 31st March 2024)
In accordance with the provisions of the German regulation on network reserve of power plants (Netzreserveverordnung) as last amended on 13th May 2019, the German national regulatory authority (Bundesnetzagentur, NRA) has examined the requirement for additional reserve power for the network reserve as determined by the German transmission system operators for the winter period 2023/2024, and has published the associated report in accordance with § 3 para 1 NetzResV.
In the report of the German NRA dated 28th April 2023, an additional demand for generation capacity for the network reserve in the total amount of 1334 MW is determined for the winter term 2023/2024, for the coverage of which an expression of interest pursuant to §4 NetzResV is initially launched. The total amount of network reserve capacity to be acquired may change depending on the sensitivity to network congestions and has to been evaluated in the context of possible alternatives within the congestion management as well as the current political situation.
The German transmission system operators hereby invite interested power plant operators to submit expressions of interest in accordance with § 4 (2) NetzResV for the participation of their power plants in the network reserve in the period from 2nd May 2023 to 15th May 2023. To submit an expression of interest, interested operators are required to complete the documents supplied for this purpose and return send them to the responsible transmission system operator, both electronically and in printed form.
- for Germany: the relevant connecting transmission system operator
- for Italy and Switzerland: TransnetBW GmbH
- for France and Luxemburg: Amprion GmbH
Details of the specific prerequisites and requirements for the plants and/or plant operators, including the geographical network region in question and the technical parameters involved, are included in the documents provided.
The deadline for submitting expressions of interest for participation in the network reserve is 15th May 2023. The electronic submission of the signed documents is relevant for the on-time submission.
Possible resulting contracts will depend on approval by the German NRA, especially regarding the selection of plant operators to be contracted and resulting financial obligations upon the responsible transmission system operator. There is no legal entitlement to conclude a contract.
The German transmission system operators reserve the right to change the published information without further announcements.
Contact person for expressions of interest to be submitted to ÜNB:
Contacts
TenneT Network Reserve
TenneT TSO GmbH
Bernecker Straße 70
95448 Bayreuth
Expired calls for interest
Test | |||
---|---|---|---|
Delivery period | Tender deadline | Inclusion date of plants into network reserve | Requirement in MW |
Winter 2022/2023 | May 15th, 2022 | October 1st, 2022 | 1424 |
Winter 2017/2018 | May 15th, 2017 | October 1st, 2017 | 1600 |
Winter 2019/2020 | May 15th, 2015 | October 1st, 2019 | 1600 |
Winter 2016/2017 | May 15th, 2015 | October 1st, 2016 | 3198-4212 |
Winter 2015/2016 | May 15th, 2015 | October 1st, 2015 | 489-1388 |
1st quarter 2015 | October 15th, 2014 | January 1st, 2015 | 545 |
Winter 2017/2018 | May 15th, 2014 | October 1st, 2017 | 3076 |
Winter 2015/2016 | May 15th, 2014 | October 1st, 2015 | 1414 |
Winter 2015/2016 | May 15th, 2014 | October 1st, 2015 | 1439 |
Winter 2014/2015 | May 15th, 2014 | October 1st, 2014 | 64 |